CITY COUNCIL AGENDA COMMUNICATION |
|
| | | | | | | | AGENDA DATE: | AugustĀ 25, 2020 |
|
| | | | | | | | SUBJECT: | Award Bid and Authorize the City Manager to Execute a Contract with Mart, Inc., for Fire Station #5 Parking Lot Restoration in the Amount of $121,686. |
|
| | | | | | | | STAFF RESOURCE: | Chris Flanigan, Director of Engineering |
|
| | | | | | | | PREVIOUS COUNCIL ACTION: | On July 9th, 2019, Council authorized the issuance and sale of City of Allen, Texas, Tax Notes, Series 2019, including the adoption of an Ordinance authorizing the issuance of such notes, establishing parameters for the sale and issuance of such notes and delegating certain matters to authorized officials of the City. |
|
| | | | | | | | ACTION PROPOSED: | Award Bid and Authorize the City Manager to Execute a Contract with Mart, Inc., for Fire Station #5 Parking Lot Restoration in the Amount of $121,686. |
|
| | | | | | | | BACKGROUND
Fire Station #5 and it's parking lot were constructed in 2012. In the past couple of years, the parking lot at Fire Station 5 has experienced shifting in the pavement. Staff engaged a geotechnical firm to investigate the cause and provide a solution. It was discovered that the base material under the pavement has subsided, and the rainwater cistern under the parking lot is leaking and a contributing factor. This contract work will proceed to follow the recommendation of the geotechnical engineer, remove the cistern outright, bring in fill material, and replace with concrete pavement. Given the leaks that have developed in the cistern, it is not being used for irrigation for the fire station site any longer.
A Request for Bid (RFB) process was used in acquiring pricing for this project. One (1) proposal was received. Even though only one bid was received, the proposal was within the range expected for this extensive amount of work, given the extent of excavation and sensitivities associated with working in such close proximity to a working fire station. The only responsive proposal is listed below.
Solicitation # 2020-6-110
Bidder
|
Bid Total
|
Mart, Inc.
|
$121,686
|
|
| | | | | | | | BUDGETARY IMPACT
This project will be funded with FY19 Tax Notes, approved by the Allen City Council on July 9th 2019. The project was listed in the recommended projects.
PO2007 - Fire Station #5 Parking Lot Restoration
Project Expenses
|
Description
|
Expense
|
Construction
|
$121,686
|
|
| | | | | | | | STAFF RECOMMENDATION
Staff recommends that the City Council award bid and authorize the City Manager to execute a contract with Mart, Inc., for Fire Station #5 parking lot rehabilitation in the amount of $121,686.
|
| | | | | | | | MOTION
I make a motion to award bid and authorize the City Manager to execute a contract with Mart, Inc., for Fire Station #5 parking lot rehabilitation in the amount of $121,686.
|
|