Item Coversheet

CITY COUNCIL AGENDA COMMUNICATION
AGENDA DATE:AprilĀ 23, 2019
SUBJECT:

Award Bid and Authorize the City Manager to Execute a Contract with ANA Site Construction, LLC for Northbrook Court Drainage Improvements in the Amount of $247,223.

STAFF RESOURCE:

Chris Flanigan, Director of Engineering

ACTION PROPOSED:

Award Bid and Authorize the City Manager to Execute a Contract with ANA Site Construction, LLC for Northbrook Court Drainage Improvements in the Amount of $247,223.




BACKGROUND

The City of Allen was contacted by homeowners in the Wimberly (Twin Creeks Estates) neighborhood with concerns about fast-moving water through their backyards.  A tributary of Rowlett Creek, which long-existed before the homes were built, runs through the backyards in a drainage easement.  The tributary is shallow and wide, so when a rain event occurs, the spread of water is not necessarily deep, but it is intimidating because of the width of the flow of water (occupying nearly the entire backyard).  Furthermore, the leaves and other matter that flows through their backyards toward Rowlett Creek is caught on the homeowner's fences, creating a difficult maintenance situation, beyond the reasonable effort for an average homeowner.  The result is backyards that cannot ever achieve a stand of grass, remain muddy and wet continuously, and requires a solution that exceeds the abilities of a single homeowner to undertake alone.

 

The residents desire a piped solution to route the overland stormwater flows in a buried pipe through their backyards and are willing to contribute to the cost.  The public development project agreement that outlines the terms of payment between the City of Allen and property owners is a companion item on the same agenda.

 

On Wednesday December 12, 2018, a total of eight bids were received, the three lowest and responsive bids are below:

 

Bid 2019-11-4
Contractor Calendar Days Bid Amount
ANA Site Construction, LLC  60  $ 224,748.25
GRod Construction, LLC  90  $ 233,921.00
FNH Construction, LLC  125  $ 269,358.00

BUDGETARY IMPACT

Funding will come from Unallocated CIP Funds.

 

DR1804 - Northbrook Court Drainage Improvements

Award Itemization

 Bid Amount  $ 224,748.25 
 Bid Contingency (10%)   $ 22,474.75 
 TOTAL AWARD AMOUNT  $ 247,223.00 

     


STAFF RECOMMENDATION

Staff recommends that Council award bid and Authorize the City Manager to execute a contract with ANA Site Construction, LLC for the Northbrook Court Drainage Improvements in the amount of $247,223.


MOTION

I make a motion to award bid and authorize the City Manager to execute a contract with ANA Site Construction, LLC for the Northbrook Court Drainage Improvements in the amount of $247,223.



ATTACHMENTS:
Description
Location Map
Standard Form of Agreement
Prevailing Proposal