Item Coversheet

CITY COUNCIL AGENDA COMMUNICATION
AGENDA DATE:AprilĀ 23, 2019
SUBJECT:

Award Bid and Authorize the City Manager to Execute a Contract with J.R. Stelzer for Repainting and Minor Repairs of the Bethany Water Tower and Stacy Ground Storage Tank #3 in the Amount of $1,123,782.

STAFF RESOURCE:

Chris Flanigan, Director of Engineering

ACTION PROPOSED:

Award Bid and Authorize the City Manager to Execute a Contract with J.R. Stelzer for Repainting and Minor Repairs of the Bethany Water Tower and Stacy Ground Storage Tank #3 in the Amount of $1,123,782.




BACKGROUND

The Bethany Water Tower and Stacy Ground Storage Reservoir #3 underwent routine annual inspections by Texas Tank Services. In the resulting report, the coating system of both facilities were identified as needing attention. For the competitive bid process, Birkhoff, Hendricks & Carter, L.L.P. was contracted to further evaluate the tanks and review of the flow meters in order to prepare drawings and specifications for all necessary improvements. The final project includes Bethany Water Tower interior/exterior repaint and Stacy Ground #3 exterior repaint and minor tank repairs.

 

A Request for Proposal (RFP) process was used in acquiring pricing for this project. On April 3, 2019, a total of 6 proposals were received. The three (3) lowest and responsive proposals are below:

 

Solicitation #2019-2-33 
 Bidder Bid Total
 J.R. Stelzer  $ 1,021,620
 CFG Industries, LLC $ 1,117,950
 D&M TANK LLC $ 1,307,130

 

Contractors were given a specific start and end date for the project. A committee was formed to evaluate proposals on a 100-point scale, derived from an evaluation of both price and references from past work experiences. Recommendation to award J.R. Stelzer is based on results of evaluation points and record of having satisfactorily completing similar projects.


BUDGETARY IMPACT

This project will be funded through both FY18 and FY19 water and sewer operating revenues, outlined in the capital improvement program and the annual budget.

 

 WA1903 - Bethany Water Tower and

Stacy Ground Storage Reservoir #3 Repaint

Project Expenses

 Description Expense
 Contract Amount  $ 1,021,620
 10% Contingency $ 102,162
 Total $ 1,123,782

STAFF RECOMMENDATION

Staff recommends that Council authorize the City Manager to award bid and execute a contract with J.R. Stelzer for Bethany Water Tower and Stacy Ground #3 Repaint and Minor Repairs in an Amount of $1,123,782.


MOTION

I make a motion to authorize the City Manager to award bid and execute a contract with J.R. Stelzer for Bethany Water Tower and Stacy Ground #3 Repaint and Minor Repairs in an Amount of $1,123,782.



ATTACHMENTS:
Description
Location Map
Prevailing Proposal
Standard Form of Agreement