SUBJECT:

Award Bid and Authorize the City Manager to Execute a Contract with Wall Enterprises for the Construction of the Reed Park East Renovations in the Amount of $352,435.

STAFF RESOURCE:

Brian Bristow, Assistant Director of Parks and Recreation

Matt McComb, Landscape Architect

Debra Morris, Purchasing Manager

ACTION PROPOSED:

Award Bid and Authorize the City Manager to Execute a Contract with Wall Enterprises for the Construction of the Reed Park East Renovations in the Amount of $352,435.




BACKGROUND

Reed Park East is located at the corner of Allen Heights Dr. and Rivercrest Blvd. The park was originally built in 1999. The tennis court has endured a full lifetime of use and is due for resurfacing to better serve its users. Due to the park's age, we will be upgrading most of the amenities and adding new ones to improve the park's use.

 

The construction plans are for a turnkey project that includes resurfacing of the tennis courts, a new fence, shade structure, retaining wall, new walkways, site furnishings, and trail along Allen Heights Drive.

 

The Purchasing Division received three (3) qualified responses and recommends awarding the bid to the lowest and most qualified bidder, Wall Enterprises, who submitted a bid for this project for a total of $352,435.  Staff anticipates completion of this project in March of 2018.

 

Contractor

Base Bid w/Alternates

Calendar Days

Wall Enterprises

$352,435

154

North Rock Construction, LLC

$441,703

90

Schmoldt Construction

$603,665

215



BUDGETARY IMPACT

Funding for the improvements to Reed Park East are included in the Parks CIP and are comprised of a combination of CDC Funds and Park Dedication Fees.


STAFF RECOMMENDATION

Staff recommends the City Council award bid and authorize the City Manager to execute a contract with Wall Enterprises for the Construction of the Reed Park East Renovations in the Amount of $352,435.


MOTION

I make a motion to Award Bid and Authorize the City Manager to Execute a Contract with Wall Enterprises for the Construction of the Reed Park East Renovations in the Amount of $352,435.