CITY COUNCIL AGENDA COMMUNICATION
AGENDA DATE:May 9, 2017
SUBJECT:

Award Bid and Authorize the City Manager to Execute a Contract with O3 Concrete Contractors, LLC., for the Chelsea Boulevard and Allen Commerce Parkway Intersection Improvements in the Amount of $275,966.11.

STAFF RESOURCE:

Chris Flanigan, Director of Engineering

ACTION PROPOSED:

Award Bid and Authorize the City Manager to Execute a Contract with O3 Concrete Contractors, LLC., for the Chelsea Boulevard and Allen Commerce Parkway Intersection Improvements in the Amount of $275,966.11.




BACKGROUND

The need for this intersection improvement has come about due to the AISD construction of the new Elementary No. 18 (Preston Elementary).  The school is scheduled to be open for classes in Fall 2018.  Traffic associated with the new school is expected to increase along Chelsea Boulevard, which will cause congestion at the Chelsea Boulevard and Allen Commerce Parkway intersection in its current 3-way stop condition.

 

The Chelsea Boulevard Intersection Project will improve the existing intersection by removing the northbound and southbound stop condition.  This project will extend the existing northbound lanes just north of Allen Commerce Parkway, removing the sharp curve in the intersection.  This intersection improvement will aide in traffic flow as the new Preston Elementary opens by not requiring Northbound and Southbound traffic to stop at the Allen Commerce intersection. The project also includes the extension of a 12" water line.

 

On April 26, 2017, a total of six (6) bids were received and the three (3) lowest are as follows:

Solicitation # 2017-3-58

Bidder

Bid Total

O3 Concrete Contractors, LLC.

$ 275,966.11

XIT Paving and Construction, Inc.

$ 308,804.00

Jim Bowman Construction Company, LP.

$ 309,587.45


BUDGETARY IMPACT

The estimated project costs and funding are illustrated in the following tables:

 

ST1703 - Chelsea Boulevard and Allen Commerce Parkway
Intersection Improvements

Project Cost Estimate

Fund

Amount

Design

$ 12,000.00

Construction

$275,966.11

Laboratory Testing

$10,033.89

TOTAL

$298,000.00

 

 

ST1703 - Chelsea Boulevard and Allen Commerce Parkway
Intersection Improvements

Proposed Funding

Fund

Amount

Non-Bond Roadway Fund (ST1202)

$ 112,000

Roadway Impact Fees (Quad 1)

$ 134,926

Water Impact Fees

$ 51,074

TOTAL

$ 298,000


STAFF RECOMMENDATION

Staff recommends that the City Council authorize the City Manager to execute a contract with O3 Concrete Contractors, LLC. for the Chelsea Boulevard and Allen Commerce Parkway Intersection Improvements in the amount of $275,966.11.


MOTION

I make a motion to authorize the City Manager to execute a contract with O3 Concrete Contractors, LLC. for the Chelsea Boulevard and Allen Commerce Parkway Intersection Improvements in the amount of $275,966.11.





ATTACHMENTS:
Description
Location Map
Standard Form of Agreement
Bid Tally